Renovation of some Quarters at the Government Estate at Okwe

Planning

Planning Rationale: 2020 Contracts to SMEs
Awarding Organisation: Ministry of Housing

Tenders

Tender status: complete

Awards

Contract Award Amount: ₦34,940,304.75
Date Awarded: 2020-02-07
Supplier: Verge Blue Enterprise
Supplier's Locality: Agbor
Supplier's address : 18 Powerline, BojiBoji Owa,Agbor
Award Status : active

Contract

Contract name : Renovation of some Quarters at the Government Estate at Okwe
Contract Status : terminated
Contract amount : ₦34,940,304.00
Contract Start Date: 2020-03-31
Contract End Date: 2020-08-30
Contract duration (Days) : 152