Construction of Seven (7) Nos simple Solar Scheme(SSMBH) in 7 Communities

Planning

Planning Rationale: 2020 SME PROJECTS
Awarding Organisation: Rural Water Supply Agency
Budget description: DSTG 2020 Approved Budget

Tenders

Tender title: Construction of seven (7) Nos simple Solar Scheme(SSMBH) in 7 Communities
Tender status: complete
Number of Tenders: 3

Awards

Contract Award Amount: ₦2,080,000.00
Date Awarded: 2020-09-07
Supplier: Emimarvis Global Resource
Supplier's address : Suite 11 12 Jamat Plaza
Award Status : active

Contract

Contract name : Construction of seven (7) Nos simple Solar Scheme(SSMBH) in 7 Communities
Contract Status : terminated
Contract amount : ₦24,230,000.00
Contract Start Date: 2020-09-07
Contract End Date: 2020-12-23
Contract duration (Days) : 100