Construction of Isheagu/Ewulu Road, Phase 1: (From Ughelli/Asaba Expressway Junction through Isheagu to Ewulu) in Aniocha South

Planning

Planning Rationale: MONTHLY PROCUREMENT REPORT
Awarding Organisation: MINISTRY OF WORKS

Tenders

Awards

Contract Award Amount: ₦2,507,585,921.35
Date Awarded: 2021-01-27
Supplier: Dora-Dan Global Resources
Award Status : active

Contract

Contract name : Construction of Isheagu/Ewulu Road, Phase 1: (From Ughelli/Asaba Expressway Junction through Isheagu to Ewulu) in Aniocha South
Contract Status : active
Contract amount : ₦2,507,585,921.35
Contract Start Date: 2021-01-27
Contract End Date: 2023-01-27

Implementation

Dataset

Download Documents
No documents uploaded yet.