Construction of Central Workshop for Faculty of Engineering at University of Delta, Owa Alero Campus.
Planning
Planning Rationale: MONTHLY PROCUREMENT REPORTAwarding Organisation: MINISTRY OF HIGHER EDUCATION
Tenders
Tender status: completeProcurement method: selective
Number of Tenders: 4
Awards
Contract Award Amount: ₦362,566,814.27Date Awarded: 2021-08-20
Supplier: REGINALO NWACHUKWU ENTERPRISE
Supplier's Locality: AGBOR
Supplier's address : 150 OLD LAGOS ASABA ROAD, BOJI BOJI, OWA
Award Status : active
Contract
Contract name : Construction of Central Workshop for Faculty of Engineering at University of Delta, Owa Alero Campus.Contract Status : active
Contract amount : ₦362,566,814.27
Contract Start Date: 2021-08-20
Contract End Date: 2022-08-20
Contract duration (Days) : 365
Implementation
Dataset
Download Documents
No documents uploaded yet.Next Project: » Construction of a Gate House at University of Delta, Agbor.