Construction of 3600meters of overhead high voltage lines and installation of 1no. 500kv, 11/0.415kv transformer substation at the government hospital, Owa-Alero in Ika North-East LGA (HRC 566/Vol.II)
Planning
Planning Rationale: MONTHLY PROCUREMENT REPORTAwarding Organisation: MINISTRY OF HEALTH
Tenders
Tender status: completeProcurement method: selective
Number of Tenders: 3
Awards
Contract Award Amount: ₦30,988,151.24Date Awarded: 2021-05-25
Supplier: Chrisrho Enterprises
Award Status : active
Contract
Contract name : Construction of 3600meters of overhead high voltage lines and installation of 1no. 500kv, 11/0.415kv transformer substation at the government hospital, Owa-Alero in Ika North-East LGA (HRC 566/Vol.II)Contract Status : active
Contract amount : ₦30,988,151.24
Contract Start Date: 2021-05-25
Contract End Date: 2021-11-25
Contract duration (Days) : 180